• Acoustic Emission Inspection for 1 Above Ground Storage Tank Bottom was carried out successfully at a refinery at Malaysia.
  • Acoustic Emission Inspection for 1 in-service Pressure Vessel carried out successfully at a refinery at Fujairah, UAE. The findings were corroborated by subsequent PAUT inspection.
  • Acoustic Emission Inspection for 3 Above Ground Storage Tank Bottom was carried out successfully at a refinery at Fujairah, UAE.
  • Acoustic Emission Inspection for 32 Kelly Tubes was carried out successfully on a vessel in Malaysia.
  • Three (3) heat exchanger APR Inspections were successfully conducted in Malaysia for a total of 2200 tubes.
  • Four (4) heat exchanger tube APR inspection was successfully carried out in Indonesia for a total of 3200 tubes.
  • One (1) LRUT inspection carried out successfully on Crude Oil pipelines in Abu Dhabi, UAE.
  • One (1) LRUT inspection was successfully carried out in Egypt for 500m above ground Main Oil Line.
  • Four (4) RFT inspections conducted successfully for heat exchanger tubes in Kazakhstan.
  • Three (3) IRIS inspections conducted successfully for heat exchanger tubes in Kazakhstan.
  • Two (2) NFT inspections conducted for heat exchanger tubes successfully in Kazakhstan.
  • Three (3) ECT inspection of Heat Exchanger Tubes was successfully carried out at Gas processing plant in UAE.
  • One (1) ECT inspection of Chiller Tubes carried out at a Gas Processing plant in UAE.
  • One (1) PEC inspection on insulated pipelines conducted successfully in Egypt.
  • One (1) CUI inspection for storage tank and vessel by PEC LYFT conducted successfully in Indonesia.
  • One (1) Corrosion Under Pipe Support (CUPS) inspection of Pipes, supports, etc. carried out an offshore facility in UAE.
  • Two (2) PEC inspection on sphere legs carried out successfully in UAE.
  • One (1) PEC inspection on insulated pipelines covering 13 equipments was successfully carried out in Egypt.
  • One (1) PEC for baseline pipeline inspection carried out successfully in Malaysia.
  • One (1) CUI inspection for insulation pipes conducted successfully in Indonesia by PEC technique.
  • Five (5) encoded thickness measurement survey of drums / columns / reboilers / tanks / UT-MAT area / bends conducted successfully in Kazakhstan.
  • One (1) PAUT C-Scan Corrosion Mapping conducted successfully in Malaysia.
  • One (1) PAUT for detection of Hydrogen Damage Mechanisms (HIC) inspection service conducted successfully in Malaysia.
  • Three (3) PAUT Hydroform Corrosion Mapping inspections service carried out successfully at UAE.
  • Two (2) PAUT inspections service for pressure vessels carried out successfully at UAE.
  • One (1) PAUT inspection of welds of spherical tanks conducted successfully in UAE.
  • One (1) PAUT inspection of pipe to fitting weld carried out successfully in UAE.
  • One (1) ACFM Inspection for pressure vessels carried out successfully at a gas processing plant in UAE.
  • Four (4) UT,MT,PT,VT,HT, RT inspections carried out successfully in Kazakhstan.
  • One (1) UTG inspection for pipe thickness measurement conducted successfully in Indonesia.
  • One (1) MPI Inspection carried out successfully in UAE.
  • Two (2) SECT inspection conducted successfully in UAE.
  • One (1) UT, MT, PT & Borescope inspection on vessels carried out successfully in Malaysia.
  • One (1) AUT – Rapid Motion Scanner (RMS) inspection of spherical tanks carried out successfully in Egypt.
  • Five (5) Remote Visual Inspection (RVI) conducted successfully in Indonesia.
  • Three (3) Remote Visual Inspection (RVI) on pipelines carried out successfully in UAE.